SCOPE AND PURPOSE
This "Method Statement" covers the on-site installation of FAN COIL UNITS (FCU) and the requirements of checks to be carried out.
REFERENCE DOCUMENTS
- Project Specifications
- Approved shop drawings (latest revision)
- Approved material submittals
GENERAL
Fan Coil Units are generally installed in locations shown in drawings, serving both concealed and exposed areas for supplying cold, dehumidified air to conditioned spaces.
EQUIPMENT
- Drilling Machine
- Spirit Level
- Scaffolding
- Hand Tools of Tradesmen
RESPONSIBLE PERSONNEL
- Project Engineers
- Construction In-Charge
- Site Engineer / Site Supervisor
- QA/QC Inspectors
- Safety Officer
- Site Foremen
- Pipefitters
- Helpers
METHOD OF PRE-INSTALLATION
- Ensure that the approved material required to carry out the work is available.
- Prior to the commencement of work, the area and access will be inspected to confirm that the site is ready to commence the work.
- The Site Engineer will check all relevant documentation and materials applicable to particular sections of work before commencement.
- Physical verification of material will be carried out for any damage before taking it from stores.
- The Site Engineer / Supervisor will give the necessary instructions to the tradesmen and provide the necessary construction / shop drawings.
- The Site Engineer / Supervisor will also check that the tools and equipment available comply with contract requirements.
- The Site Supervisor will explain to tradesmen the safety precautions to be observed.
METHOD OF INSTALLATION
- Prior to the commencement of work, coordination will be done with other services.
- Determine the position of the Fan Coil Unit on the ceiling and mark the location of supports as per the approved shop drawings.
- Prepare and fix the Fan Coil Unit supports as per the approved construction drawings and specifications.
- Ensure that vibration isolators of the approved make, type, and model are installed.
- Install the Fan Coil Units by lifting them slowly using suitable lifting aids, if necessary. The manufacturer's recommendations shall be followed during installation.
- Any cut edges of angles, channels, or threaded rods will be touched up with zinc-rich paint.
- Fan Coil Units will be connected with piping connections, including valves and accessories, as indicated in the approved shop drawings.
- Ensure that dielectric unions are used for piping connections to FCUs, where required by the approved design.
- FCU valve packages shall be provided with a drain pan as shown in the approved shop drawings.
- Ensure that drain connections are made with an adequate slope and a running trap.
- Complete the duct connections to Fan Coil Units as shown in the approved shop drawings.
- Complete the electrical power connection, including earthing in all respects, as per the approved electrical drawings and manufacturer's recommendations.
- Ensure that adequate space for the maintenance of Fan Coil Units and valve packages is available.
- Install the thermostat control units as per the shop drawings / Architectural PE/SS/FM drawings.
- Complete the BMS interfacing with DDC controllers as per the approved BMS drawings.
QUALITY CONTROL
- The QC Engineer, along with the Project Engineer and Site Supervisor, will monitor that all components are installed as per the contract specifications and approved submittals.
- An Inspection Request (IR) shall be submitted to the Main Contractor / Consultant.
SAFETY
- Work will commence as per safety regulations laid down in the contract specifications and project safety plan.
- A proper safety harness shall be used and secured, if required.
- All personal protective equipment shall be used as appropriate according to the nature of the job.
- Housekeeping shall be maintained to a good standard, and all waste materials and debris shall be removed.