HVAC: AHU Installation

Contents

Table of Contents

SCOPE AND PURPOSE

This "Method Statement" covers the on-site installation of AIR HANDLING UNITS (AHUs) and the requirements of checks to be carried out.

REFERENCE DOCUMENTS

  • Project Specifications
  • Approved shop drawings (latest revision)
  • Approved material submittals

GENERAL

Air Handling Units are generally installed in locations shown in drawings, serving corridors and supplying treated fresh air to the lobbies and apartments located on various floors.

EQUIPMENT

  • Drilling Machine
  • Spirit Level
  • Lifting Equipment (Cranes)
  • Rollers
  • Scaffolding
  • Hand Tools of Tradesmen

RESPONSIBLE PERSONNEL

  • Project Engineers
  • Construction In-Charge
  • Site Engineer / Site Supervisor
  • QA/QC Inspectors
  • Safety Officer
  • Site Foremen
  • Pipefitters
  • Helpers

METHOD OF PRE-INSTALLATION

  • Ensure that the approved material required to carry out the work is available.
  • Check the nameplate details of Air Handling Units against the approved shop drawings, schedules, and material submittals before installation.
  • Prior to the commencement of work, the area and access will be inspected to confirm that the site is ready to commence the work.
  • The Site Engineer will check all relevant documentation and materials applicable to particular sections of work before commencement.
  • Physical verification of material will be carried out for any damage before taking it from stores.
  • The Site Engineer / Supervisor will instruct the tradesmen and provide the necessary construction / shop drawings.
  • The Site Engineer / Supervisor will also check that the tools and equipment available comply with contract requirements.
  • The Site Supervisor will explain to tradesmen the safety precautions to be observed.
  • Ensure that all lifting operations are carried out as per the approved procedure.

METHOD OF INSTALLATION

  1. Prior to the commencement of work, coordination will be done with other services.
  2. Check the foundation of the AHU for size, orientation, and finishes as per the approved shop drawings.
  3. Make sure that AHUs are free from damage and that all internal components are complete and in good condition.
  4. AHUs will be installed in the locations specified in the approved shop drawings.
  5. Install the AHUs on a concrete foundation using suitable equipment recommended by the manufacturer (e.g., rollers / jacks). The manufacturer's recommendations will be followed during the erection of the AHU.
  6. Multi-section units will be joined as per the manufacturer's instructions. Ensure that shipping bolts are removed where required by the manufacturer.
  7. Ensure the orientation of AHUs is as per the approved shop drawings during installation.
  8. Serrated rubber pads (Neoprene Isolators) will be provided below AHUs.
  9. AHUs that are ceiling-suspended will be mounted using threaded rods, spring hangers, etc., as per the approved details.
  10. Any cut edges of angles, channels, or threaded rods will be touched up with zinc-rich paint for ceiling-suspended AHUs.
  11. Connect all piping and accessories to AHUs as per the approved shop drawings.
  12. Ensure that dielectric unions / flanges are used for piping connections to AHUs, as required by the approved design.
  13. Ensure that drain connections are made with an adequate slope and an approved U-trap.
  14. Complete the duct connections to Air Handling Units as shown in the approved shop drawings.
  15. Filters of the specified sizes will be provided.
  16. Check that adequate space for the maintenance of Air Handling Units is provided as per the approved shop drawings.
  17. Complete the electrical power connection, including earthing in all respects, as per the approved electrical drawings and manufacturer's recommendations.
  18. Complete the BMS interfacing with DDC controllers as per the approved BMS drawings.

QUALITY CONTROL

  • The QC Engineer, along with the Project Engineer and Site Supervisor, will monitor that all components are installed as per the contract specifications and approved submittals.
  • An Inspection Request (IR) shall be submitted to the Main Contractor / Consultant.

SAFETY

  • Work will commence as per safety regulations laid down in the contract specifications and project safety plan.
  • A proper safety harness shall be used and secured, if required.
  • All personal protective equipment shall be used as appropriate according to the nature of the job.
  • Housekeeping shall be maintained to a good standard, and all cut lengths and debris shall be removed.
  • All lifting operations shall be monitored by the Safety Officer.

‍